Background
The Harbour Authority of Cape St. George was formed and incorporated in 1999. The mandate of the authority is to manage the harbour facilities at De Grau. The Authority was formed in response to the federal governments plans to have harbour facilities managed by local fisherpersons. In addition to securing improvements to the harbour infrastructure the committee is responsible for establishing user fees, collecting same and ensuring all expenses are paid. An arrangement with local fisherpersons and local fish buyers have been organized to have harbour fees automatically paid from point of fish sales (the fish buyers). This ensures the long term viability of the harbour authority. To date the harbour authority has been fiscally responsible. The following individuals serve as volunteers on the harbour authority:
President |
Leon Simon |
Vice-President |
George Young |
Secretary-Treasurer |
Jasen Benwah |
Member at large |
Bernard Benoit |
Member at large |
Harold Rouzes |
Member at large |
Octave Benoit |
Town Representative |
Ted Rouzes |
The following strategic plan represents the efforts of the harbour authority's strategic planning session which was facilitated by the local department of Industry, Trade & Rural Development.
Goal
Objectives:
Activity by Priority | Potential Funding Sources |
---|---|
Development Plan | Year One |
Repair existing wharf (walkway & road improvements) | SCH, HACSG,LMDA |
Install new wharf ladders | SCH, HACSG |
Repair winch house | HACSG |
Activity by Priority | Potential Funding Sources |
---|---|
Development Plan | Year Two |
Commence Phase I of Eastern Breakwater | SCH |
Dredging of Harbour | SCH |
Install water system on wharf | HACSG,SCH |
Concrete platform for oil tank | HACSG |
Install cold room | HACSG, KF |
Install electrical hook-up on wharf | SCH |
Activity by Priority | Potential Funding Sources |
---|---|
Development Plan | Year Three |
Expand Building & accommodate washrooms, showers, laundry mat | SCH, HACSG, LMDA, DFO, DFA |
Construct wheelchair ramp to building | SCH, HACSG |
Activity by Priority | Potential Funding Sources | |||||
---|---|---|---|---|---|---|
Development Plan | Year Four | |||||
Construction of multi purpose gear storage building (60 x 24 x 8) | SCH, HACSG, LMDA | |||||
Complete landscaping around harbour facility (parking area, clean-up, etc.) | HACSG | |||||
Develop interpretation board on fish species | HACSG, LMDA | |||||
Acronyms: SCH - Small Craft Harbours HACSG - Harbour Authority of Cape St. George DFO - Department of Fisheries & Oceans DFA - Department of Fisheries & Aquaculture KF - Kendall's Fisheries LMDA - Labour Market Development Agreement |
Many thanks go out to the NL Provincial Dept. of Industry and Trade Rep. Mark Felix for his work in developing this plan